Object
Publication Plan November 2022
Representation ID: 5308
Received: 22/12/2022
Respondent: Miller Homes
Agent: Pegasus Group
Legally compliant? Not specified
Sound? No
Duty to co-operate? Not specified
Policy is not consistent with national policy as currently drafted and should be amended as suggested
The policy makes a blanket assumption that new education infrastructure will be required from all new development. However, any such provision to be delivered via S106 legal agreement, must have regard to the tests within CIL Regulation 122 and the policy should make this explicit. Furthermore, the policy should also recognise that new infrastructure will only be required from new development where it can be demonstrated that existing capacity to accommodate growth does not currently exist.