Preferred Options November 2021

Search representations

Results for Highways England search

New search New search

Support

Preferred Options November 2021

Question 10

Representation ID: 947

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

As no additional employment sites are identified above additional supply a transport evidence base for employment sites is not required.

Support

Preferred Options November 2021

Question 7

Representation ID: 955

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

Policy SA1 - Likely to impact on M54 Junctions 2 & 3 and on A449 north of M54 Junction 2
Policy SA2 - Will directly impact on A449 and M54 Junction 2 and abuts the M54
Policy SA3 - Main traffic impacts likely to be at M54 Junction 1
Policy SA4 - Greatest traffic impacts likely to be at M6 Junction 13 and on A5/A449 Gailey roundabout. Proposed green infrastructure abuts M6.

Have sought to agree a SATURN model with SCC to determine trip distribution and assignment for Local Plan sites. This data is then provided to strategic sites to carry out their own assessments, including mitigation works on SRN.

Detailed specific comments provided for SA2 and SA4.

Support

Preferred Options November 2021

Question 8

Representation ID: 957

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

Early consultation will be required on sites to ensure appropriate assessments are carried out to identify the form of any mitigation required for the SRN and appropriate boundary treatments to SRN.

Support

Preferred Options November 2021

Question 9

Representation ID: 958

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

Early consultation will be required on sites to ensure appropriate assessments are carried out to identify the form of any mitigation required for the SRN and appropriate boundary treatments to SRN.

Support

Preferred Options November 2021

Question 6

Representation ID: 959

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

Given the location it can be expected that any new settlement within this area of search will have material implications for the SRN. When further details emerge National Highways should be consulted at the earliest possible stage.

Support

Preferred Options November 2021

Question 11

Representation ID: 960

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

Welcome the commitment to sustainable transport and active travel set out in Policy HC19 and Policy EC11, but further detail will be required as these are developed further.

Support

Preferred Options November 2021

Question 1

Representation ID: 962

Received: 01/02/2022

Respondent: Highways England

Representation Summary:

The Secretary of State's decision regarding the M54/M6 link road is expected in April 2022, not October 2021 as set out in the IDP.